How we collected, unpacked, stored and delivered two vessels of steel for a steel importer in May 2026, with every container dehired and every delivery made on schedule.
A steel importer had two vessels of rebar, coils and reo mesh landing within days of each other. It needed all 61 containers collected, unpacked under cover, dehired and delivered on schedule, without running up detention or damaging the steel.
1
Before the ships arrived we lined up wharf slots, extra labour and an additional 16-tonne forklift.
2
Containers were collected from the wharf on our own trucks as each one became available.
3
Rebar, coils and reo mesh were unpacked under cover with forklifts sized for each load.
4
Steel was stored under cover by product, so each order could be picked without double handling.
5
Each empty went back to its nominated park as soon as its unpack finished.
6
Orders went out on our flat beds as the customer called them, every one on schedule.
Collected from the wharf and unpacked at our depot.
Both ships landed within days of each other.
From first collection to last delivery.
Every delivery on schedule, with an extra 16 t forklift.
Customer
Steel importer
Volume
61 containers from 2 vessels
When
May 2026, over 10 days
Products
Rebar, steel coils and reo mesh